The CDM 2007 Regulations apply to all construction projects where people are at work. For further information seedomestic clients.
The Regulations are divided into five parts:
Part 1 – application of the Regulations and definitions.
Part 2 – general duties that apply to all construction projects.
Part 3 – additional duties that only apply to notifiable construction projects, ie those lasting more than 30 days, or involving more than 500 person days of construction work.
Part 4 – practical requirements that apply to all construction sites.
Part 5 – transitional arrangements and revocations.