How can I check if a site I am contracted to work on has been registered with an F10

I have been contracted to work on a domestic refurb site in central London .

On surveying the site, there is evidence of lack of PM, lack of any safety and no CDM.

When i ask if an F10 has been registered, I am reassured but not given any evidence.

How can I check if an F10 has been registered for that site.

1 Like

CDM 2015 Regulation 6(3)(b) requires that a copy of the F10 be clearly displayed in the site office where it can be read by any worker engaged in the construction work.