Welcome to ReachBack
|
|
1
|
2482
|
28 November 2021
|
NEC4 Accepted Programme
|
|
0
|
18
|
26 April 2024
|
Query on add and delete referencing a tender rate
|
|
1
|
40
|
26 April 2024
|
Option E Programmes
|
|
0
|
19
|
26 April 2024
|
NEC4 PSC Option E Programme changes
|
|
0
|
18
|
26 April 2024
|
NEC Option A Compensation Events with drawing revisions- How is Fee applied
|
|
1
|
39
|
26 April 2024
|
NEC4. Limitation of delay damages under X7
|
|
5
|
219
|
25 April 2024
|
PSC4 - People or Subcontractor
|
|
1
|
44
|
25 April 2024
|
'Smash and grab' payment applications ad infinitum
|
|
0
|
57
|
23 April 2024
|
Planned Completion & Completion Date
|
|
0
|
41
|
23 April 2024
|
People Rates for Specialist Sub-contractor
|
|
0
|
39
|
23 April 2024
|
Evidence for Compensation Event Quotations
|
|
0
|
48
|
23 April 2024
|
NEC4 Subcontract Option A - Activity Schedule Clause 55
|
|
7
|
297
|
23 April 2024
|
Contract Programme - Access Dates
|
|
0
|
36
|
23 April 2024
|
Provisional items under NEC Type A contract
|
|
3
|
269
|
23 April 2024
|
NEC 4 Option D Early Completion
|
|
2
|
235
|
23 April 2024
|
NEC ECC: Disallowed cost of Defects due to failure by Contractor to Comply with Specification
|
|
8
|
3184
|
23 April 2024
|
Issue of GC to add an additional scope against existing scope of an EI
|
|
2
|
402
|
23 April 2024
|
NEC3 Option B, Clause 60.6
|
|
2
|
81
|
23 April 2024
|
What happened to this forum?
|
|
3
|
195
|
19 April 2024
|
30.2 Project Manager deciding Completion
|
|
1
|
409
|
18 April 2024
|
Risk allowance under NEC
|
|
0
|
459
|
21 March 2021
|
Nec 4 pssc total liability
|
|
0
|
426
|
22 April 2021
|
PC Stopping the Works
|
|
0
|
437
|
4 June 2021
|
Ownership of the Works Information
|
|
0
|
385
|
1 June 2021
|
Client Design NEC3 Option A
|
|
0
|
413
|
1 July 2021
|
Option E with Schedue of Rates
|
|
0
|
349
|
4 August 2021
|
NEC4 ECC Contractors Design
|
|
0
|
342
|
7 October 2021
|
Contingency Sums Option A NEC4
|
|
0
|
431
|
1 December 2021
|
Quotation format for a subcontractor under NEC option A
|
|
0
|
377
|
29 June 2022
|