What happens if the Project Manager’s reply to a communication from the Contractor is not acceptance?
1 Like
The Project Manager should declare his reasons for withholding acceptance. The Contractor then resubmits the communication within the period for reply, taking into account the Project Manager’s reasons for withholding acceptance (see Clause 13.4).