What happens if the Project Manager does not reply to the Contractor’s notification that he has failed to reply within the time allowed?
1 Like
If the Project Manager does not reply to the notification within two weeks, and unless the quotation is for a proposed instruction or a proposed changed decision, the Contractor’s notification is treated as acceptance of the quotation by the Project Manager (see clause 62.6).