Why might the Project Manager not accept a communication from the Contractor?

Why might the Project Manager not accept a communication from the Contractor?

1 Like

The Project Manager may withhold acceptance if the communication lacks sufficient information for the Contractor to assess the submission fully (see Clause 13.4).