What are Plant and Materials?
1 Like
Clause 11.2(12) defines Plant and Materials as items that are included in the work. This is distinct from Equipment which includes items used temporarily in the construction but removed at or before Completion e.g. formwork and falsework which is struck (removed) prior to Completion would be categorised as Equipment.