Does title to Plant and Materials pass back to the Contractor if they are removed from the Working Areas?

Does title to Plant and Materials pass back to the Contractor if they are removed from the Working Areas?

1 Like

Yes - providing they are removed from the Working Areas with the Project Manager’s permission (see Clause 70.2).