In a Design & Build contract, the Works Information is changed following discussions between the Contractor and Designer which results in work being deleted.
If the Contractor does not notify a Compensation Event then as I see it, the only recourse is for the Supervisor to notify a defect.
Is this correct or can the PM inform the Contractor that he needs to notify a CE or can the PM notify?