AS a contractor does the Apprentice Levy qualify as a rechargeable expense under X2
1 Like
My view is yes the apprentice levy is a change in law (UK).
It is new legislation that has been introduced in the Finance Bill where there was no existing legislation.
One minor point to bear in mind is that the levy will only be a compensation event for contracts entered into before the 6th April 2017 as X2 uses the term Contract Date to draw a line in the sand.