I have seen a few questions along these lines, but just wanted to check.
We have an NEC3 with Option X2 included (this clause is not amended). Clause 19 is not applicable, as amended so Covid cannot apply. Site is in England, law is England.
We consider there has been a change in law (the Coronavirus Act 2020) thus option X2 applies, and thus it is a compensation event. The Employer is saying the Coronavirus Act 2020 does not prevent/ impact construction works, so Option X2 does not apply. When we mentioned the CIC guidance, they have said that is just guidance so not a change in law so again option X2 does not apply.
In my mind, it is still a compensation event as the law has changed (the Coronavirus Act 2020) post contract date.
The Project Manager may then seek to argue that the law change has not had an impact on the Prices/ Planned Completion Date, when he is assessing the same.
Do people agree with this interpretation? Do other people think Covid 19 is an option X2 event in England?
I would also be interested in people’s thoughts on whether we can argue that the new guidance is a change in law? As i do think we might struggle to show the Coronavirus Act 2020 has impacted (as it does not mention construction/ prevent anything) if we cannot also refer to the guidance.