NEC ECC: Termination of works by Employer Option A (NEC3)

Who determines the payment on termination and how is this done?

The Project Manager determines the amount due in accordance with the termination table in Clause 90.2, and certifies payment within 13 weeks of termination, as required by Clause 90.3.