BI Toolkit
BI Toolkit
ReachBack
Does a contractor will have a right to charge additional payment for additional work instructed?
Legal and Disputes
Contractor Claims
Legal_Expert
18 January 2013 10:28
2
Yes, under the terms of most contracts.
Related topics
Topic
Replies
Views
Activity
NEC ECC: Do we have to do extra instructed works and how should it be assessed?
NEC3 and NEC4 Contracts
2
3438
3 September 2017
NEC ECC: Does Contractor have to follow an instruction after Completion to do extra work if they don’t really want to?
Compensation Events
1
2481
16 November 2017
Does the Contractor pay the excess if the Price for Work Done is greater than the Total of the Prices?
NEC3 and NEC4 Contracts
1
661
15 October 2012
When an architect is charged extra fess for work which results from a contractor breaching certain obligations, can the employer recover these fees from the contractor?
JCT Contracts
1
444
5 February 2013
Under JCT SBC16, is the contractor bound to carry out additional work not measured as part of the Employers tender documents(BoQ)?
JCT Contracts
1
459
10 April 2017