BI Toolkit
BI Toolkit
ReachBack
Does a contractor will have a right to charge additional payment for additional work instructed?
Legal and Disputes
Contractor Claims
Legal_Expert
18 January 2013 10:28
2
Yes, under the terms of most contracts.
Related topics
Topic
Replies
Views
Activity
JCT MW2016 - Additional works not instructed
General
1
530
3 June 2020
NEC ECC: Do we have to do extra instructed works and how should it be assessed?
NEC3 and NEC4 Contracts
2
3407
3 September 2017
NEC ECC: Does Contractor have to follow an instruction after Completion to do extra work if they don’t really want to?
Compensation Events
1
2471
16 November 2017
Under JCT SBC16, is the contractor bound to carry out additional work not measured as part of the Employers tender documents(BoQ)?
JCT Contracts
1
458
10 April 2017
NEC3 ECC Option A - Unistructed works carried out by the Contractor
Compensation Events
4
572
6 July 2020