ReachBack
Does a contractor will have a right to charge additional payment for additional work instructed?
Legal and Disputes
Contractor Claims
Legal_Expert
18 January 2013 10:28
2
Yes, under the terms of most contracts.
Related Topics
Topic
Replies
Views
Activity
NEC ECC: Do we have to do extra instructed works and how should it be assessed?
NEC3 and NEC4 Contracts
2
3061
3 September 2017
Under JCT SBC16, is the contractor bound to carry out additional work not measured as part of the Employers tender documents(BoQ)?
JCT Contracts
1
417
10 April 2017
NEC3 ECC Option A - Unistructed works carried out by the Contractor
Compensation Events
4
506
6 July 2020
Additional works to be carried out by Others
Compensation Events
3
237
11 July 2023
New to jct contracts - Adding an addumdum for additional services
General
1
706
26 February 2016