NEC3 ECC Option C: Does WAO apply to Agency Supplied Workers?
|
|
3
|
1784
|
3 November 2017
|
NEC ECC: Deemed Programme Acceptance
|
|
3
|
3333
|
3 November 2017
|
NEC ECC: Tyre puncture repair included in Defined Cost?
|
|
3
|
1245
|
3 November 2017
|
If the Contracts (Rights of Third Parties) Act 1999 is used does this negate the need to Collateral Warranties?
|
|
1
|
637
|
2 November 2017
|
NEC ECC: When pricing a CE when would the people fee percentage apply? Is it applied to every CE?
|
|
2
|
4201
|
2 November 2017
|
NEC ECC: The Contractor's Activity Schedule does not list out all the activities required for the work
|
|
2
|
999
|
2 November 2017
|
NEC ECC: Subcontractor Damage to Site
|
|
2
|
508
|
2 November 2017
|
NEC ECC: Can you give me an example of when Y(UK)3 would be used as to who might be named, and what benefit or right they then have?
|
|
1
|
3622
|
1 November 2017
|
NEC ECC: Employer's Liability for Sub-Contractor's Cost where Contractor has gone into Administration
|
|
1
|
480
|
31 October 2017
|
NEC ECC: Contractor has not acted on a PM's instruction does this effect the value of the CE?
|
|
1
|
706
|
31 October 2017
|
NEC ECC: Can a existing Risk Register item extend contract duration after completion cert issued?
|
|
1
|
457
|
30 October 2017
|
NEC ECC: How to calculate the total of the Prices under Option C?
|
|
1
|
7498
|
27 October 2017
|
NEC3 ECC: Can non-implemented compensation events be included on a Contractor's revised programme?
|
|
3
|
2451
|
26 October 2017
|
NEC ECC: Should Terminal Float on Sectional Completion impact Terminal Float on Contract Completion?
|
|
5
|
1648
|
25 October 2017
|
JCT - Assumption in design
|
|
1
|
584
|
24 October 2017
|
NEC ECC: X7 Delay Damages Estimate - can this include the Employers staff?
|
|
2
|
612
|
24 October 2017
|
NEC ECC: Does the Project Manager's Compensation Event description have to match the Contractors notification
|
|
6
|
869
|
23 October 2017
|
NEC ECC: To what level of evidence should I be expected to provide when submitting a compensation event for increased costs due to delays in the programme by six months
|
|
3
|
1179
|
23 October 2017
|
NEC ECC: Project Manager's instructions without drawings
|
|
3
|
824
|
23 October 2017
|
NEC ECC: CECA Rates - Equipment exceeding Purchase cost
|
|
3
|
2224
|
23 October 2017
|
NEC ECC - How a Contractor gain profit under option A
|
|
1
|
540
|
19 October 2017
|
NEC ECC: Access Dates
|
|
2
|
3102
|
18 October 2017
|
NEC ECC: apprenticeship levy a Compensation Event
|
|
3
|
787
|
16 October 2017
|
NEC ECC: Role of the Supervisor - How far are the 'testing requirements' defined in the Works Information?
|
|
4
|
1345
|
14 October 2017
|
NEC ECC: Supervisor to confirm what's in the Works Information ONLY
|
|
3
|
667
|
14 October 2017
|
NEC ECC: Can I change the price for an activity using a CE if a PMI is issued delaying a Key Date
|
|
1
|
389
|
13 October 2017
|
NEC ECC: Option A - split payment of Compensation Events
|
|
1
|
2225
|
13 October 2017
|
NEC ECC: Deleted 18.1
|
|
1
|
812
|
13 October 2017
|
NEC ECC: Can retention be held under NEC3 option X16 following defects sign off?
|
|
1
|
2696
|
13 October 2017
|
NEC ECS: Unaccepted Programme
|
|
2
|
763
|
13 October 2017
|