I am drafting a Scope for an NEC4 Option C contract including the secondary clause X22. Whilst drafting I am referring to the preparing the NEC ECC guide that NEC provides. In the guide, NEC advises the following sections to be add to the Scope:
- S100 Description of the works
- S200 General Constraints
- S300 Contractor Design
- S400 Completion
- S500 Programme
- S600 Quality Management
- S700 Testing and Inspections
- S800 Management of the Works
- S900 Working with the Client and others
- S1000 Services provided by the client
- S1100 Health and Safety
- S1200 Subcontracting
- S1300 Title
I have also add a new section in accordance with the guide āS 2500 Early Contractor Involvementā. What I would like to know isā¦do I need to repeat all of the relevant information in Section S 100 - S 1300 within S 2500 or does all of the Scope above apply during stage 1 (X22).
For example there are requirements for the Contractor to provide site welfare in the general scope under S 1000, but these wonāt necessarily be required in stage 1 as the space will not be available until stage 2.
A lot of the information included in S 100 - S 1300 is mostly relevant to Construction/Stage 2 so I do not want to be caught out.