|
NEC ECC: How to calculate the Gain Sharing when Contractor Defects are involved
|
|
1
|
2303
|
14 June 2019
|
|
NEC ECC: Can PM designate certain brand of consumables in PM offices in an Option C contract?
|
|
2
|
1099
|
14 June 2019
|
|
NEC PSC: What relevance are Employer expenses in CD1?
|
|
3
|
560
|
14 June 2019
|
|
NEC ECC - Payment on consumables
|
|
2
|
3382
|
13 June 2019
|
|
NEC ECC - payment inspection
|
|
2
|
3686
|
10 June 2019
|
|
NEC ECC: BoQ items doubled up?
|
|
1
|
498
|
10 June 2019
|
|
NEC ECC: When is the assessment date?
|
|
1
|
4214
|
3 June 2019
|
|
NEC ECC: Option B:- Compensation Events and missing items
|
|
2
|
2259
|
23 May 2019
|
|
NEC4 ECC: Next Payment Date option C
|
|
1
|
2244
|
22 May 2019
|
|
NEC3 ECC Option C: Are professional subscriptions / memberships Defined Cost?
|
|
1
|
772
|
1 May 2019
|
|
NEC ECC: What is WAO applied to
|
|
1
|
1854
|
15 April 2019
|
|
NEC ECC: Claiming for prelims when contract period is extended?
|
|
1
|
1365
|
4 April 2019
|
|
NEC ECC: Payment for Deposit Charges
|
|
4
|
676
|
2 April 2019
|
|
NEC ECC: Can the client limit payment to agreed target value only on option C.
|
|
5
|
584
|
19 March 2019
|
|
NEC ECC: Specified material now on long lead time - is this a CE?
|
|
1
|
483
|
10 March 2019
|
|
NEC PSC: What is the risk to Consultants under option E for defects i.e. can costs be disallowed?
|
|
1
|
3118
|
8 March 2019
|
|
NEC ECS: In an Option C subcontract, when is the Pain/Gain assessment made & paid?
|
|
2
|
601
|
7 March 2019
|
|
NEC ECC: Payment for Attendance at Subcontractor Works
|
|
1
|
790
|
26 February 2019
|
|
NEC ECC: Option C - Off Site Fabrication - Sub-Contract Fee or Direct Fee?
|
|
1
|
428
|
25 February 2019
|
|
NEC ECC: If Direct Fee on an Option C is not stated as being Fixed or Variable in the Contract Data, is there a default position?
|
|
1
|
350
|
6 February 2019
|
|
NEC ECS: Contractor delay in assessing Compensation Events
|
|
1
|
497
|
4 February 2019
|
|
NEC ECC: How does clause 25.2 work in practice under option C?
|
|
1
|
924
|
31 January 2019
|
|
NEC ECC: Is a Contractor paid for CE works that are not yet agreed?
|
|
2
|
2766
|
31 January 2019
|
|
NEC4 ECC Option C - Inspection of records of Defined Cost
|
|
1
|
1359
|
23 January 2019
|
|
NEC ECC: Does a CE need to implemented prior to payment?
|
|
2
|
3438
|
22 January 2019
|
|
NEC ECC: Withheld Monies - Not Disallowed Cost - Option C
|
|
2
|
1508
|
18 January 2019
|
|
NEC ECC: Can payment be withheld for a time related activity that can never be completed?
|
|
3
|
830
|
16 January 2019
|
|
Fidic red book and NEC3 comparison
|
|
2
|
760
|
9 December 2018
|
|
NEC ECS: Payment of Option B
|
|
1
|
720
|
4 December 2018
|
|
NEC TSC: View on whether direct fee is applicable to payment
|
|
2
|
1050
|
25 November 2018
|