Are loss and expense claims important?
|
|
1
|
512
|
18 January 2013
|
Are there any issues to take into consideration regarding circumstances at the time of performance, and are there any legislative cases to cite as precedence in this area?
|
|
1
|
593
|
18 January 2013
|
Should earnings and expenditure be regarded separately?
|
|
1
|
508
|
18 January 2013
|
What does 'Quantum Meruit' refer to?
|
|
1
|
566
|
18 January 2013
|
Are there any issues related to interest charges for which contractors need to have awareness?
|
|
1
|
492
|
18 January 2013
|
If the contractor or sub-contractor need borrow money at excessively high rates, can this be recovered?
|
|
1
|
442
|
18 January 2013
|
When are finance charges likely to be accepted?
|
|
1
|
507
|
18 January 2013
|
Under what legislation are interest charges dealt with?
|
|
1
|
517
|
18 January 2013
|
What are formula claims?
|
|
1
|
521
|
18 January 2013
|
What impact does the alleged poor performance of a contractor have on the acceleration process?
|
|
1
|
455
|
18 January 2013
|
Can a contractor have a negative impact upon a global claim?
|
|
1
|
505
|
18 January 2013
|
Why might a global claim fail?
|
|
1
|
515
|
18 January 2013
|
What is the definition of a global claim?
|
|
1
|
617
|
18 January 2013
|
Can disruption attract any prolongation costs?
|
|
1
|
558
|
18 January 2013
|
Why is it important to provide a well presented and evidenced claim?
|
|
1
|
576
|
18 January 2013
|
To whom should a financial claim for loss and expense be submitted to?
|
|
1
|
534
|
18 January 2013
|
What element forms the basis of many disputes in construction and engineering contracts?
|
|
1
|
464
|
18 January 2013
|
Is there an alternative way of calculating profit, aside from subtracting costs to date from the sum stipulated in the contract?
|
|
1
|
479
|
18 January 2013
|
When a contractor makes a claim for loss of profit what should the calculation be based on
|
|
1
|
444
|
18 January 2013
|
What are the consequences of an an employer deciding to take work from one contractor on site and give it to another?
|
|
1
|
440
|
18 January 2013
|
Under what circumstances could a contractor argue his / her entitlement to loss of profit?
|
|
1
|
462
|
18 January 2013
|
How can 'direct costs' be defined?
|
|
1
|
519
|
18 January 2013
|
When does loss of profit as a head of claim under the IFC form of contract constitute a valid claim?
|
|
1
|
478
|
18 January 2013
|
Does a contractor will have a right to charge additional payment for additional work instructed?
|
|
1
|
499
|
18 January 2013
|
What influence does the the Housing Grants, Construction and Regeneration Act, 1996 have on the process?
|
|
1
|
522
|
18 January 2013
|
Are there any other parties to whom the Housing Grants, Construction and Regeneration Act 1996 does not apply?
|
|
1
|
514
|
18 January 2013
|
Are there any cases in which the need for a contract to be treated as evidence in writing under the Construction Act do not apply?
|
|
1
|
430
|
18 January 2013
|
What criteria need to be satisfied in order for a contract to be treated as evidence in writing under the Housing Grants, Construction and Regeneration Act 1996?
|
|
1
|
496
|
18 January 2013
|
To which construction contracts does the unamended Act apply under the Housing Grants, Construction and Regeneration Act 1996?
|
|
1
|
494
|
18 January 2013
|
Which specific operations are excluded from being considered part of a construction contract in legal terms under the Housing Grants, Construction and Regeneration Act 1996?
|
|
1
|
568
|
18 January 2013
|