With regards to the rectification period, what occurs if the contractor is in breach of contract?

Where the contractor is in breach of the contract, the defect (or rectification) period only allows him to carry out that work at his own expense. It must be recognised that the end of the defects period does not terminate the contractor’s liability to rectify defects that have arisen as a result of his breach of contract.