Can an employer make a claim for negligent design, and if so how does this work?

Yes. Where the contractor and his sub contractor undertake design and that design fails to meet the criteria in full or fails in its entirety the employer shall be entitled to make a claim for damages that flow from that negligent design.

In the Fidic Yellow and Silver books you may also make use of SC 5.8 [Design Error].