The Works Information includes a hard-copy drawing, which references another drawing which has not been included in hard-copy.
Is the drawing referenced included into the Works Information?
The Works Information includes a hard-copy drawing, which references another drawing which has not been included in hard-copy.
Is the drawing referenced included into the Works Information?
I would say ‘Yes’ on the same basis that standard specifications are often referenced from the ‘pack’ given to the tendering contractors without the need to specifically forward them to the tendering contractors. Likewise, when the contract is signed.