We have a sub-contract on the above basis.
We have a set of tender drawings on which the sub-contract was based and were subsequently issued a set of construction issue drawings under cover of a variation. The contractor’s QS has completely re-measured the package under the variation which has resulted in a reduction to our account.
My argument is that only change to each drawing can be valued and that they are not entitled to remeasure as we are not on an article 3B.
Am I correct and what is “the Adjustment Basis” as stated in article 3A?
We do have a Contract Sum Analysis with quantities and rates, however, should they have later proved to be incorrect my argument is that that is that is moot and it was merely a means to arrive at a contract sum on which we were taking the risk.