Why might the Project Manager not accept a revision of the Activity Schedule?
A reason for not accepting a revision of the Activity Schedule is that:
It does not comply with the Accepted Programme
Any changed Prices are not reasonably distributed between the activities or
The total of the Prices is changed (see Clause 54.3).