On what grounds can a Contractor in an ECC contract submit a revision of the Activity Schedule to the Project Manager for acceptance
1 Like
When the activity schedule no longer reflects how they plan to carry out the works - they can change it and resubmit for acceptance in accordance with clause 54.1.
Only reason for not accepting it will be:
- it is not in line with programme
- does not add up to the total of the Prices
- costs are not evenly distributed