Who is responsible for work that the Contractor has subcontracted?
1 Like
The Contractor is completely responsible for all work under the ECC. If he subcontracts work, he remains accountable as if he had not subcontracted. Furthermore, the Subcontractor’s employees and equipment are treated as if they are the Contractor’s (see Clause 26.1).