I am currently working for a Subcontractor employed by main Contractor under a NEC3 ECS Option A subcontract.
We have recently raised several EWN’s and NCE’s regarding damaged (mainly accidental) to our subcontract works caused by other subcontractors. We do however note that in some instances we have not been able to demonstrate which particular party is responsible for such damage due to the large number of trades currently on site.
The Contractor has subsequently rejected all our NCE’s raised in connection with this matter stating that pursuant to clause 82.1, all repairs (irrespective of who caused the need for repair in the first instance) is a Subcontractor risk and consequently all repair works should be undertaken at our own expense; something we consider unreasonable.
We maintain that as we are not responsible for the site nor the security of it, do not have exclusivity to any particular area of site and have no contractual relationship with other trades, therefore the above must be considered a Contractor’s risk and as such, further to clause 60.1 (14), we should be entitled to a compensation event when carrying out repair works arising from damaged caused by others. However, the difficultly we are having is that we cannot pinpoint this to a specific Contractor’s risk as listed under clause 80.1.
We anticipate that as works progress, this problem will become more prevalent so would be grateful for any guidance pertaining to this matter.