What should the Contractor include on his revised programme?
Clause 32.1 states that on each revised programme the Contractor must show: the progress of each operation and how it affects the timing of remaining work; how any compensation events or early warning matters have affected the work; how he plans to correct notified Defects and deal with delays; and additional changes which he plans to make to the Accepted Programme.
Of course, every programme should also comply with 31.2 as well as any other specific requirements stated within the Works Information.