The project manager instructs to submit a revised programme under clause 32.2 to include the impact of additional treatment works based off results found when on site post tender.
The project manager was advised of an additional number of days delay on the programme within the narrative included with the submission. The project manager accepts the programme on the basis that the new planned completion date includes timescales for some assumptions and as such will be requesting a new programme and clarifying the assumptions (but never did), the project manager requested the contractor take this into account in order to move the planned completion back closer to the contract completion date. The project manager also mentions the current contract completion date has not been affected and remains. Any changes to this date will be treated through the NCE process.
A portion of this time has been claimed under a CE relevant to the treatment works which subsequently led to the PMI. At a later date it is realised the programme has been as built incorrectly therefore the programme impact has not been fully claimed for
The project manager instructs to submit a revised programme under clause 32.2 to include the impact of additional treatment works based off results found when carrying out scoped works on site, post tender.
This was provided by the contractor within 2 weeks from instruction. The project manager was advised of an additional number of days delay within the programme itself and programme narrative included with the submission. The project manager accepted the programme on the basis that the new planned completion date includes timescales for some assumptions and as such will be requesting a new programme clarifying the assumptions (but never did), the project manager requested the contractor take this into account in order to move the planned completion back closer to the contract completion date. The project manager also mentions the current contract completion date has not been affected and remains. Any changes to this date will be treated through the NCE process.
A portion of this time has been claimed under a CE relevant to the treatment works which subsequently led to the PMI. At a later date it is realised the programme has been as built incorrectly therefore the programme impact has not been fully claimed for
Can the contractor submit an NCE for the additional delay previously not claimed due to the additional delay being associated with works not relating to the request of the revised programme i.e. resequencing is related to additional treatment works to the full works area which were meant to be carried out pre-possession. The resequencing meant that items previously not on the critical path now fell onto the critical path to allow time for the treatment works to be completed prior to commencing with contracted works but the CE submitted had not allowed for the further delay to the programme caused by moving other activities which fell onto the critical path. This was not realised until a date past the 8 week notification period but the project manager had not notified the contractor of the delay under Clause 61.1 which states that the project manager is obliged to notify the contractor of any delay arising from an instruction, at the time the instruction is given despite being advised of this with the submission of the revised programme requested under clause 32.2
Can the contractor still raise a sperate NCE for this issue without being time barred and can they recover their costs for this?