What is the procedure if the Contractor wants to replace a person named to do a job stated in the Contract Data?
1 Like
This procedure is outlined in Clause 24.1. The Contractor will give the name, relevant experience and qualifactions of the planned replacement to the Project Manager for him to accept or reject.