Why might the Project Manager not accept the Contractor’s replacement person?

Why might the Project Manager not accept the Contractor’s replacement person?

1 Like

Clause 24.1 outlines that the Project Manager may not accept a replacement person if his qualifications and experience are not as good as his predecessor’s. However, a Project Manager may still accept a person whose qualifications or experience are inferior to the previous person if the Project manager is satisfied that said person will be suitable for the position.