Can the Contractor appoint a Subcontractor on the proposed subcontract conditions before the Project Manager has accepted them?
1 Like
No. According to Clause 26.3, the Project Manager must accept the proposed subcontract conditions before the Contractor can appoint the Subcontractor on those terms.