Why might the Project Manager not accept the Contractor’s proposed appointment of a Subcontractor?
1 Like
The Project Manager may not accept the Subcontractor if his appointment will not allow the Contractor to Provide the Works (see Clause 26.1). Where the subcontracted work is for a small amount of technically simple work, the Project Manager’s acceptance acceptance of the Subcontractor may be merely a matter of procedure.