BI Toolkit
BI Toolkit
ReachBack
Sub contractor equipment cost
NEC3 and NEC4 Contracts
SOCC SSOCC
Neil_Earnshaw
14 January 2021 11:20
2
See my response to this question:
show post in topic
Related topics
Topic
Replies
Views
Activity
Defined Cost - Percentages - Option A contract
SOCC SSOCC
1
844
31 December 2020
NEC3 ECC - Shorter Schedule of Cost Components Percentages
SOCC SSOCC
2
3909
8 January 2021
NEC ECC: Do Labour rates in the SSOCC include the direct fee?
SOCC SSOCC
3
960
3 May 2019
NEC ECS: Option A Subcontract CE Quotation
Compensation Events
1
883
22 July 2019
NEC3 ECC: Direct/Subcontractor fee percentages when using Option A
Compensation Events
1
7347
8 January 2016