ReachBack
Sub contractor equipment cost
NEC3 and NEC4 Contracts
SOCC SSOCC
Neil_Earnshaw
14 January 2021 11:20
2
See my response to this question:
show post in topic
Related topics
Topic
Replies
Views
Activity
Defined Cost - Percentages - Option A contract
SOCC SSOCC
1
800
31 December 2020
NEC3 ECC - Shorter Schedule of Cost Components Percentages
SOCC SSOCC
2
3688
8 January 2021
NEC3 ECC: Direct/Subcontractor fee percentages when using Option A
Compensation Events
1
7244
8 January 2016
NEC ECS: Option A Subcontract CE Quotation
Compensation Events
1
857
22 July 2019
NEC3 ECC: How is a CE assessed under Option A when only the percentage for people overhead and the Equipment % have been inserted?
Compensation Events
3
2046
1 March 2017