NEC3 ECC - Shorter Schedule of Cost Components Percentages

Taking each component in turn:

People

  • Amount paid by Contractor for Contractor’s people + % people overheads = sub total for Contractor’s people

  • Amount paid by Subcontractor for Subcontractor’s people + % people overheads = sub total for Subcontractor’s people

Plant and Materials

  • Payments for purchasing Plant and Materials = sub total for Plant and Materials

Design

  • (Total hours worked by Subcontractor’s employees x hourly rates in Contract Data) + % design overheads = sub total for design

The direct and subcontracted fee percentages are then applied to the relevant components to arrive at a total, in your case as the fee percentages are the same it doesn’t matter but it would be important to apply it correctly if they were different.

2 Likes