I am trying to find an answer to what I think should be a simple query when using ECC Option A.
Contract Data Part 2 asks for a Direct Fee Percentage and a Subcontracted Fee Percentage.
Cl. 11.2(8) states that the Fee is the sum of the amounts calculated by applying the subcontracted fee percentage to the Defined Cost of subcontracted work and the direct fee percentage to the Defined Cost of other work.
Cl. 11.2(22) states that Defined Cost is the cost of the components in the SSCC whether the work is subcontracted or not excluding the cost of preparing compensation events.
When assessing compensation event I usually go through the following process:
People – apply % for people overheads
Equipment – apply % adjustment for equipment
Materials – no %
Total – apply Direct Fee %
Subcontractors – apply subcontractors fee %
As I read the above clauses in conjunction with the guidance notes I am now coming round to the idea that I should be assessing compensation events in this way:
People (including Subcontractors People) – apply % for people overheads
Equipment (including Subcontractors Equipment) – apply % adjustment for equipment
Materials (including Subcontractors Materials) – no %
Total – apply Direct Fee %
If this is the case how, if at all, is the Subcontractors Fee % applied when using Option A?