If and Option B Bill has items with zero quantity against them, are they remeasurable in the same manner as the other items.
Welcome to the Group
On an Option B the Bill should be produced by the Employer to be reflective of the Works Information and the work to be carried out. The Bill is not intended to operate with rate only items. Therefore if there is a zero quantity the item of work cannot be required, ie it is not in the Works Information, and because its not required it can’t be remeasurable.