Under option B what happens if a work item is included in the Works Information but was excluded in the Bill of Quantities?
In this case the temporary sign is on the drawings but not included in the bill.
An error in the BoQ should be corrected by the PM in accordance with clause 60.6 and would be a compensation event.
An error would include an omission from the BoQ.
You should check the method of measurement to check that the item of work should, in accordance with the method, be itemised in the BoQ.
Thankyou, Dave CEN been issued as above