Community - pre-empting a discrepancy/discussion that may give rise to a contractual debate further down the line.
Form of Contract - Option B
The works Information contains schedule of attendances to be provided by the Contractor. However, a specific item of note does not have a BOQ item whereby the Contractor can recover based on works performed. Would also add the BOQ has not been measured in accordance with the stated method of measurement otherwise the item should have been in the BOQ.
I assume the Contractor will request a CE when it becomes apparent that there is no BOQ item, however the client will not be changing the WI.
How should this be handled - The client will no doubt initially attempt the position that the Contractor has priced the WI and as such is Contractors risk to price all requirements?
Thanks in advance.