NEC ECC: Is there provision is included in the NEC for nomination of subcontractors

1 Like

No. Reason is that if the Employer really wants a particular specialist contractor, rather than create a shotgun marriage where contractually the Subcontractor is answerable to the main Contractor but commercially (sort of) to the Employer, the Employer should control the interface themselves.