I am aware that there is no provision in NEC3 ECC for nominated sub-contractors. However, if a compensation event is notified to introduce a nominated sub-contractor into the Works Information, is the Contractor still responsible for Providing the Works as if he had not sub-contracted (Clause 26.1) and as such carry all risks associated with the conditions of the sub-contract not aligning with the main conditions of contract or does the Employer carry these risks?
Typical examples might be:
a) Defects Date in the sub-contract is earlier that the Defects Date in the main contract.
b) There are no delay damages in the sub-contract