Can a contractor reduce a rate on a LSFP if an element of the works was not carried out? would this be classified as risk?
Related topics
Topic | Replies | Views | Activity | |
---|---|---|---|---|
FIDIC Red Book: Difference between lump sum contract and Fixed sum contract | 1 | 5627 | 23 March 2018 | |
FIDIC RED BOOK - CONS Contract - CONTRACTOR DESIGN WORKS | 1 | 875 | 8 January 2019 | |
Client requesting rate breakdown for bespoke item in bill - NEC 3 Short Form | 2 | 124 | 28 June 2024 | |
JCT: What is reasonable cost breakdown to provide against lump sum prices for variation comparison | 2 | 1838 | 10 July 2020 | |
NEC3 ECC: Reduction in lump sum cost on an Option A contract | 2 | 1130 | 22 July 2016 |