Can a contractor reduce a rate on a LSFP if an element of the works was not carried out? would this be classified as risk?
Related topics
| Topic | Replies | Views | Activity | |
|---|---|---|---|---|
| FIDIC Red Book: Difference between lump sum contract and Fixed sum contract | 1 | 5667 | 23 March 2018 | |
| FIDIC RED BOOK - CONS Contract - CONTRACTOR DESIGN WORKS | 1 | 884 | 8 January 2019 | |
| Client requesting rate breakdown for bespoke item in bill - NEC 3 Short Form | 2 | 129 | 28 June 2024 | |
| JCT: What is reasonable cost breakdown to provide against lump sum prices for variation comparison | 2 | 1870 | 10 July 2020 | |
| NEC3 ECC: Reduction in lump sum cost on an Option A contract | 2 | 1131 | 22 July 2016 |