If the Project Manager instructs additional tests to those stated in the Works Information, and a Defect is found, is it a compensation event?
If the Project Manager instructs additional tests and a Defect is found, is it a compensation event?
1 Like
No. If a Defect is discovered by additional tests requested by the Project Manager, it is not a compensation event (see Clause 60.1(10)).