The Supervisor has instructed the Contractor to search for a defect and no defect is found. Is this a compensation event?

The Supervisor has instructed the Contractor to search for a defect and no defect is found. Is this a compensation event?

1 Like

Until the defects date, the Supervisor may instruct the Contractor to search for a Defect (see Clause 42.1). If no defect is found and the Contractor has given sufficient notice of doing work obstructing a required test or inspection, then the event is a compensation event (see Clause 60.1 (10)).