Can the Project Manager instruct additional tests to those stated in the Works Information?

Can the Project Manager instruct additional tests to those stated in the Works Information?

1 Like

Yes. He can do this by changing the Works Information. If no Defects are subsequently found however (providing it’s not a repeat test for a corrected Defect), it is a compensation event (see Clause 60.1(1))