CECA rates contract data part 2

Hi

If there is a published list stated in contract data pt 2 is it correct that only those rates are used to value CE’s or can the schedule of cost components be used?

Thanks

The published list of Equipment contained in Data Part 2 is for use as Defined Cost in Options A and/or B under the Shorter Schedule of Cost Components. Therefore if you are on an Option A or B the published list should be used, if you are on an Option C or D then the Schedule of Cost Components should be used unless there is agreement to use the published list.

1 Like