NEC ECC: Tender Letter with Clarification not in the contract
|
|
2
|
767
|
20 September 2017
|
NEC ECC: Option A vs. Option C Subcontract Fee %
|
|
1
|
1216
|
19 September 2017
|
NEC ECC: Can a PM impose a date whereby a CE must be completed?
|
|
2
|
635
|
19 September 2017
|
NEC ECC: Does an Early Warning constitute a notice under clause 61.3
|
|
2
|
1400
|
19 September 2017
|
NEC ECC: Can float be generated on the critical path and used to mitigate a CE
|
|
1
|
737
|
18 September 2017
|
NEC ECC: Can Clients insist on Contractor's using NEC Contracts in their supply change?
|
|
3
|
442
|
18 September 2017
|
NEC ECC: Can time bar principles be applied to accepted CE's?
|
|
2
|
1160
|
15 September 2017
|
NEC ECS: The Contractor is paying 3 months late and not issuing a pay less notice
|
|
3
|
655
|
14 September 2017
|
NEC ECC: How do you deal with increase in subcontract rate due to termination of the subcontractor
|
|
3
|
468
|
14 September 2017
|
NEC Supply Contract: Who is a Subcontractor?
|
|
1
|
1103
|
13 September 2017
|
NEC ECC: Method of measurement and payment under Option A and C?
|
|
2
|
1129
|
13 September 2017
|
NEC ECC: Where would the compiler specify the Method of Measurement?
|
|
1
|
1610
|
11 September 2017
|
NEC ECC: Aggressive Client Commercial Team brought in at end of contract
|
|
3
|
614
|
7 September 2017
|
NEC ECC: Defined Cost after Completion under Option E
|
|
1
|
1322
|
7 September 2017
|
NEC ECC: Are there any occasions when you can refuse to act on an instruction?
|
|
2
|
4779
|
5 September 2017
|
NEC ECC: How long after Completion can an account be disputed?
|
|
2
|
1534
|
4 September 2017
|
NEC ECC: Assessing a rainfall 1 in 10 weather event
|
|
3
|
4921
|
3 September 2017
|
NEC ECC: Do we have to do extra instructed works and how should it be assessed?
|
|
2
|
3396
|
3 September 2017
|
NEC ECC: Can a dispute be declared after the contractual end date?
|
|
1
|
582
|
1 September 2017
|
NEC ECC: Contractor submitted a programme requesting several weeks beyond Completion Date
|
|
1
|
582
|
30 August 2017
|
NEC ECC: Removing clauses from Specification for Highway Works (MCDHW 1)
|
|
2
|
593
|
30 August 2017
|
NEC ECC: When is a defined cost a defined cost
|
|
1
|
1854
|
30 August 2017
|
NEC ECC: Using CECA rates for plant equipment
|
|
1
|
2530
|
30 August 2017
|
NEC ECC: Can history be removed from the programme?
|
|
2
|
409
|
28 August 2017
|
NEC ECC: Reject forecast of defined cost?
|
|
2
|
707
|
26 August 2017
|
NEC ECC: Can I retract a programme under option A
|
|
1
|
699
|
26 August 2017
|
NEC ECC: Defined Cost - Plant - Held in wait for start
|
|
3
|
1039
|
24 August 2017
|
NEC ECC: Option C - Effect of Penalty / Incentive on Target Cost
|
|
1
|
988
|
24 August 2017
|
NEC ECC: Should I lose the opportunity to improve on programme dates as a result of the Client not providing something by dates shown on the Accepted Programme?
|
|
1
|
466
|
24 August 2017
|
NEC Clause 60.1(12)
|
|
3
|
2906
|
18 August 2017
|