NEC3 and NEC4 Contracts Title
Topic | Replies | Views | Activity | |
---|---|---|---|---|
What happens if the Contractor removes Plant or Materials from the Working Areas without the Project Manager’s permission?
|
![]() |
1 | 727 | 15 October 2012 |
Does the Contractor require the Project Manager’s permission to remove Plant or Materials?
|
![]() |
1 | 738 | 15 October 2012 |
Does title to Plant and Materials pass back to the Contractor if they are removed from the Working Areas?
|
![]() |
1 | 663 | 15 October 2012 |
Does the Contractor’s title to Plant and Materials pass over to the Employer once they are brought onto the Working Areas?
|
![]() |
1 | 846 | 15 October 2012 |
When does the Contractor’s title to Plant and Materials which are outside the Working Areas pass to the Employer?
|
![]() |
1 | 798 | 15 October 2012 |