NEC3 and NEC4 Contracts Title
| Topic | Replies | Views | Activity | |
|---|---|---|---|---|
|
What happens if the Contractor removes Plant or Materials from the Working Areas without the Project Manager’s permission?
|
|
1 | 730 | 15 October 2012 |
|
Does the Contractor require the Project Manager’s permission to remove Plant or Materials?
|
|
1 | 740 | 15 October 2012 |
|
Does title to Plant and Materials pass back to the Contractor if they are removed from the Working Areas?
|
|
1 | 663 | 15 October 2012 |
|
Does the Contractor’s title to Plant and Materials pass over to the Employer once they are brought onto the Working Areas?
|
|
1 | 850 | 15 October 2012 |
|
When does the Contractor’s title to Plant and Materials which are outside the Working Areas pass to the Employer?
|
|
1 | 802 | 15 October 2012 |