NEC3 and NEC4 Contracts Title
Topic | Replies | Views | Activity | |
---|---|---|---|---|
Does the Contractor require the Project Manager’s permission to remove Plant or Materials?
|
![]() |
1 | 523 | 15 October 2012 |
Does title to Plant and Materials pass back to the Contractor if they are removed from the Working Areas?
|
![]() |
1 | 482 | 15 October 2012 |
Does the Contractor’s title to Plant and Materials pass over to the Employer once they are brought onto the Working Areas?
|
![]() |
1 | 650 | 15 October 2012 |
When does the Contractor’s title to Plant and Materials which are outside the Working Areas pass to the Employer?
|
![]() |
1 | 566 | 15 October 2012 |