What should the Contractor do if he discovers an object of value or of historical or other interest within the Site?
1 Like
He notifies the Project Manager and the Project Manager instructs the him how to deal with it (see Clause 73.1). The Project Manager’s instruction is a compensation event under Clause 60.1(7).