NEC ECC: How is the assessment formed when accepting a defect under Option A?
|
|
2
|
1263
|
30 March 2020
|
NEC ECC: Temporary propping of bracing - is this a Defect?
|
|
1
|
488
|
13 March 2020
|
NEC ECSC: ownership and title to construction work
|
|
1
|
451
|
2 March 2020
|
NEC ECC: Supervisor recording defects
|
|
2
|
509
|
27 February 2020
|
NEC ECC: Temporary Work Design and Clause 23.1
|
|
1
|
509
|
21 February 2020
|
NEC ECC: Can Contractor claim cost if delayed in correcting a defect that they caused?
|
|
3
|
495
|
6 February 2020
|
NEC ECC: Defects and Contractor warranties
|
|
1
|
871
|
5 February 2020
|
NEC ECC: Option C - Contractors Denies a Notified Defect is a Defect
|
|
4
|
520
|
20 January 2020
|
NEC ECC: Supervisor missed a defect, what is their liability?
|
|
3
|
750
|
6 December 2019
|
NEC ECC: Defective works
|
|
1
|
474
|
21 November 2019
|
NEC ECC: Cost of Correcting Defect
|
|
3
|
502
|
6 November 2019
|
NEC ECC: Defects, Burden of Proof
|
|
1
|
628
|
4 November 2019
|
NEC ECC: Timing for acceptance of defects 44.1
|
|
1
|
406
|
29 October 2019
|
NEC ECC: Under an Option A contract how are the Employers Costs of correcting a Defect after Completion recouped if there is no retention available?
|
|
2
|
714
|
26 October 2019
|
NEC ECC: Defiinition of 'breach' or 'non performance'
|
|
1
|
439
|
17 October 2019
|
NEC ECS: Quotation for acceptance of Defect
|
|
4
|
727
|
14 October 2019
|
NEC ECC: Contractor poor performance
|
|
1
|
1019
|
13 October 2019
|
NEC ECC; Management of latent Defects?
|
|
1
|
817
|
18 September 2019
|
NEC ECC: Accepting the correction of a Defect
|
|
1
|
753
|
13 September 2019
|
NEC ECS: Correcting a defect we know the end Client has accepted
|
|
1
|
356
|
13 September 2019
|
NEC ECC: Dual Defects Found from two different Contractors
|
|
1
|
412
|
4 September 2019
|
NEC ECC: Defect not spotted immediately
|
|
1
|
391
|
30 August 2019
|
NEC ECC: Clause 45.2 - non access to correct defect
|
|
1
|
723
|
29 August 2019
|
NEC ECC: Should the Supervisor notify the PM prior to any search of Defects?
|
|
1
|
545
|
6 August 2019
|
NEC ECC: Option A - Zero Defects
|
|
3
|
1297
|
12 July 2019
|
NEC ECC: Failed welds - whose liability?
|
|
1
|
401
|
9 July 2019
|
NEC ECC: Appointing others to correct uncorrected Defects
|
|
1
|
415
|
1 July 2019
|
NEC ECC: Correction of Defects and Design Limitations
|
|
7
|
621
|
18 June 2019
|
NEC ECC: Defects arising from poor workmanship
|
|
2
|
877
|
18 June 2019
|
NEC ECC: How to deal with the compound problems due to Contractor's Defects?
|
|
1
|
1157
|
17 June 2019
|