NEC3 ECC: Amount Due on termination of the Subcontract
|
|
1
|
3312
|
8 January 2016
|
NEC3: Employer has terminated Contractor - does this mean Sub-Contractor is automatically terminated?
|
|
1
|
1712
|
21 December 2015
|
NEC3 ECC: Can the Employer terminate a contract without notice if Completion Date has been missed?
|
|
1
|
1985
|
16 November 2015
|
Allowed costs under Termination Option E PSC
|
|
1
|
763
|
20 October 2015
|
NEC3 Supply Contract- Termination of Works / Sub-Contract Works
|
|
1
|
1343
|
22 May 2015
|
Can disallowed costs be applied under NEC3 ECC option C after a termination certificate has been issued?
|
|
1
|
1168
|
4 December 2014
|
How does the Project Manager instruct termination of the contractors sub-contractors but not the contractor
|
|
3
|
1093
|
20 November 2014
|
Deleted work is a compensation event, which is valued via the fee value of remaining works, hence is the contractor still entitled to termination costs at cl90.2
|
|
1
|
3118
|
6 November 2013
|
What constitutes substantial work, is there a method for determining substantial when instructing restart
|
|
1
|
891
|
28 October 2013
|
Can the Employer terminate if the Contractor has substantially hindered the Employer or Others?
|
|
1
|
870
|
15 October 2012
|
If termination occurs because of the Contractor’s default, is he reimbursed the cost of removing his Equipment?
|
|
1
|
704
|
12 October 2012
|
What happens to the Equipment on termination if it is owned by the Subcontractor?
|
|
1
|
721
|
12 October 2012
|
What happens to the Equipment on termination if it has been hired by the Contractor?
|
|
1
|
787
|
12 October 2012
|
Is the Contractor allowed to use the Works once termination procedures are completed?
|
|
1
|
731
|
12 October 2012
|
The Contractor has terminated because the Project Manager has instructed him to stop work . The instruction was not due to a default by the Employer or Contractor. What is the amount due?
|
|
1
|
846
|
12 October 2012
|
The Contractor has terminated because the Project Manager has instructed him to stop work or all work. The instruction was not due to a default by the Employer or Contractor. What is the termination procedure?
|
|
1
|
738
|
12 October 2012
|
The Contractor has terminated because he has been released under the law from performance of the contract (R17). What is the amount due?
|
|
1
|
707
|
12 October 2012
|
The Contractor has terminated because he has been released under the law from performance of the contract (R17). What is the termination procedure?
|
|
1
|
736
|
12 October 2012
|
The Contractor has terminated because the Project Manager has instructed him to stop work due to a default by the Employer (R19). What is the amount due?
|
|
1
|
664
|
12 October 2012
|
The Contractor has terminated because the Project Manager has instructed him to stop work due to a default by the Employer (R19). What is the termination procedure?
|
|
1
|
710
|
12 October 2012
|
The Contractor has terminated because the Employer has not paid an amount certified (R16). What is the amount due?
|
|
1
|
752
|
12 October 2012
|
The Contractor has terminated because the Employer has not paid an amount certified (R16). What is the termination procedure?
|
|
1
|
780
|
12 October 2012
|
The Contractor has terminated because the Employer has made an arrangement with its creditors. What is the amount due?
|
|
1
|
719
|
12 October 2012
|
The Contractor has terminated because the Employer has made an arrangement with its creditors. What is the termination procedure?
|
|
1
|
612
|
12 October 2012
|
The Contractor has terminated because the Employer has had a receiver appointed over its undertaking or assets (R9). What is the amount due?
|
|
1
|
694
|
12 October 2012
|
The Contractor has terminated because the Employer has had a receiver appointed over its undertaking or assets (R9). What is the termination procedure?
|
|
1
|
582
|
12 October 2012
|
The Contractor has terminated because the Employer has had an administration order made against it (R8). What is the amount due?
|
|
1
|
715
|
12 October 2012
|
The Contractor has terminated because the Employer has had an administration order made against it (R8). What is the termination procedure?
|
|
1
|
654
|
12 October 2012
|
The Contractor has terminated because the Employer has passed a resolution for winding-up (R7). What is the amount due?
|
|
1
|
784
|
12 October 2012
|
The Contractor has terminated because the Employer has passed a resolution for winding-up (R7). What is the termination procedure?
|
|
1
|
567
|
12 October 2012
|