A subcontractor has brought Equipment to site which is the responsibility of the Contractor to unload and is stated as so in the Works Information. During unloading the Contractor has damaged this Equipment. I would have initially said that this was a CE under Clause 60.1(14) (albeit damage during transit is not specifically said to be a Contractor risk). The only reference to damage to equipment referred to within the list of items under Clause 80.1 is in the context of damage post termination. This wouldn’t be a matter for the insurers as it is below the excess of the Contractor’s policy.
The question is, which is the correct categorisation of this CE?